Manufacturing Gantt Chart for Odoo 19: Setup and User Guide

A step-by-step guide to Manufacturing Gantt Chart (ki_gantt_mrp) for Odoo 19 Community: plan work orders per work center, move jobs between machines, replan by priority and spot clashes on one timeline.

Kalvyai Engineering · · 8 min read

Manufacturing Gantt Chart for Odoo 19: Setup and User Guide (cover)
On this page

Manufacturing Gantt Chart (technical name ki_gantt_mrp) adds a production planning chart to Odoo 19 Community. Every work order sits on its work center, and every manufacturing order sits on a timeline. You drag to plan, drop jobs on another machine, replan by priority in one click, and see clashes before they reach the shop floor.

This guide covers installation, setup, each main feature step by step, tips, limits and common questions.

You can buy and install the app from the store page: Manufacturing Gantt Chart.

What the app is for

Odoo Community has no production planning chart. Work orders sit in lists, so it is hard to answer simple questions:

  • Which machine is busy, and when?
  • Are two jobs planned on the same machine at the same time?
  • If I move one operation, which dates after it also need to change?
  • How do I push an urgent order to the front without replanning everything by hand?

Manufacturing Gantt Chart answers these on one screen. It uses Odoo's own planning, your existing work centers, working schedules and bills of materials. Data stays in your Odoo database; the module does not use any external service.

Who it helps

  • Production planners who decide which job runs on which machine and when.
  • Shop floor leads who need to see clashes, late components and blocked work centers early.
  • ERP admins running Odoo Community on Odoo.sh or their own server who want planning without changing bills of materials.

Requirements

  • Odoo 19.0, Community edition, on Odoo.sh or on-premise.
  • The Manufacturing app with Work Orders turned on.
  • Not supported: Odoo Online (SaaS), because it does not accept custom modules.

The module uses its own view type, so it does not replace or clash with the Enterprise Gantt view.

Installation

  1. Buy the app on the store page.
  2. Add the module to your Odoo addons.
  3. In Odoo, update the Apps list and install Manufacturing Gantt Chart.

The free Gantt View engine (ki_gantt_view) is installed automatically with it. You do not need to install it separately.

Setup

Setup takes a few minutes. Follow these steps once:

  1. Turn on Work Orders in Manufacturing > Configuration > Settings.
  2. Give each work center a working schedule. The chart uses that schedule, its time off and its time zone.
  3. Set Alternative Work Centers where a job is allowed to move to another machine. You do this in Manufacturing > Configuration > Work Centers.
  4. Confirm manufacturing orders whose bill of materials has operations.
  5. Open Manufacturing > Planning > Planning by Work Center and click Plan.

You do not need to change your bills of materials. Your operations, work centers and working schedules are used as they are.

For quick reference, these are the menu paths used in this guide:

Plain text
Manufacturing > Configuration > Settings          (turn on Work Orders)
Manufacturing > Configuration > Work Centers      (schedules, alternative work centers)
Manufacturing > Planning > Planning by Work Center
Manufacturing > Planning > Planning by Order
Manufacturing order > Gantt button

Using the app

1. Open the work center planning

Go to Manufacturing > Planning > Planning by Work Center.

You see one row per work center, idle ones included, so you can drop work on a machine that has nothing planned yet. Each bar is a work order, coloured by manufacturing order, with arrows between the steps of the same order.

How to read the chart:

  • Grey areas are outside working hours or time off (including lunch breaks).
  • A green, orange or red strip shows the load of the work center against its available hours, per day or per hour.

You can switch between day, week, month and quarter views, and zoom or fit the chart.

2. Plan what is waiting in To plan

The To plan list shows operations of confirmed orders that have no dates yet, most urgent order first.

To plan one operation:

  1. Find the operation in To plan.
  2. Drag it onto a work center row at the time you want.
  3. The operation is planned there, and the next operations of the order are planned right after it.

To plan everything at once:

  1. Click Plan.
  2. Every confirmed order without dates is planned with Odoo's own planning, most urgent first.

Note that Plan uses Odoo's planning, which can pick an alternative work center if one is set.

3. Move, resize or switch machines

Drag and drop is the main way to adjust the plan:

  • Move a bar: the work order starts at the next working hour and keeps its working time.
  • Resize a bar: this changes its expected duration, counted in working hours.
  • Drop on an alternative work center: the work order moves, and the duration of that machine is used.
  • Drop on any other work center: the move is refused with a clear message.

When you move a work order, the next operations of the same order move after it. This behaviour can be turned off.

4. Check or change a work order from its card

Click a bar to open its card. The card shows:

  • The manufacturing order and product
  • Quantity and expected time
  • Component status
  • Deadline

From the card you can start, pause, resume or finish the work order, or unplan the whole order, without leaving the chart.

For a manufacturing order that is not planned yet, its card lets you plan it or open its operations. From the chart you can also confirm, plan, unplan or check component availability of an order.

5. Replan by priority

Use Replan when the plan has drifted, for example after an urgent order arrives or a clash appears.

  1. Click Replan.
  2. Operations not started yet are freed and planned again: urgent orders first, then by deadline.
  3. Each goes to the first free slot of its work center, or of an alternative work center when that finishes sooner.

What Replan does not touch:

  • Operations already started stay where they are.
  • Each order keeps its earliest start date, so a replan never plans it too early.

If you do not like the result, undo it (see below).

6. Follow every order on one timeline

Go to Manufacturing > Planning > Planning by Order.

You get one row per manufacturing order, coloured by status, with progress, deadline flags and urgent orders starred.

To move a whole order, drag it to another day. Its operations are replanned from there. Remember that a planned order gets its length from its operations: to change how long an order takes, resize its operations, not the order bar.

7. Plan the operations of one order

Open a manufacturing order and click the Gantt button. The chart shows only that order's operations, one row each, with their work center, expected hours and status. A deadline line shows the order's deadline.

This view is useful when you discuss one order with a customer or the shop floor.

You can link two operations of the same order by dragging between their bars. Links only work inside one manufacturing order.

9. Undo, redo, export and print

  • Every move, plan, unplan and replan can be undone with the Undo button or Ctrl + Z.
  • Changes can also be redone.
  • Export the plan to Excel or print it.

Warnings and what they mean

The chart flags problems on the bars so you see them before the shop floor does:

What you see

What it means

Bar striped in red

Two work orders at the same time on one work center

Operation marked as too early

It starts before the previous operation of the order ends

Component flag on the bar

Components are missing or late

Blocked flag

The work center is blocked

Late flag / deadline flag

The order is late, or its deadline is shown on the bar

When two jobs overlap, both bars turn red-striped and you get a warning. Click Replan to clear the clashes, or move one of the jobs.

Tips

  • Set alternative work centers first. Without them, a job cannot move to another machine, and Plan and Replan have fewer options.
  • Keep working schedules accurate. The chart and Odoo's planning both rely on each work center's calendar, time off and time zone. A wrong schedule gives a wrong plan.
  • Mark urgent orders as urgent. Replan puts them first, so a correct priority saves manual moves.
  • Watch the load strip. Orange and red show where a work center is close to or over its available hours.
  • Replan freely. Since every replan can be undone, you can try it and compare.
  • Refresh when asked. If someone else changed a work order in the meantime, you are asked to refresh before your change applies.

Limitations

  • One job at a time per work center, like Odoo's own planning. Overlaps are shown as clashes, not blocked.
  • Links inside one order only. Dependencies cannot link operations of different manufacturing orders.
  • Not in the past. An order moved to a past date is planned from now.
  • Order length comes from operations. Resize the operations, not the order.
  • Odoo chooses on Plan. Plan and Replan use Odoo's planning, which can pick an alternative work center.
  • No Odoo Online. Use Odoo.sh or your own server.
  • Odoo 19 Community. This guide covers version 19.0 only.

FAQ

Which Odoo edition does it support?

Odoo Community, on your own server or Odoo.sh. It uses its own view type, so it does not replace or clash with the Enterprise Gantt view.

Which apps are needed?

The Manufacturing app with Work Orders turned on. Gantt View (ki_gantt_view, free) is installed automatically.

Which working hours are used?

The working schedule of each work center, with its time off, in the time zone of that schedule, exactly as Odoo plans work orders.

Can I move a job to another machine?

Yes, to an alternative work center of its work center or operation. Set them in Manufacturing > Configuration > Work Centers.

Who can change the plan?

Normal Odoo access rights apply. Manufacturing users can plan.

Where is the data stored?

Only in your Odoo database. The module does not use any external service.

Is it a subscription?

No, it is a one-time purchase for one Odoo database. See the store page for price and support terms.

Can I use the Gantt for other apps?

The included Gantt View engine works on any model with two date fields. A Project version is also available.

Where do I ask questions?

Write to support@kalvyai.com. If you are not sure the module fits your shop floor, tell us how you plan today and how many work centers you have, and we will tell you honestly what it can and cannot do.

How Kalvyai can help

We build and connect Odoo, ERPNext and Shopify systems, and we can help you get more out of production planning: setting up work centers, schedules and alternative machines, cleaning up bills of materials, or custom changes beyond what the module does. Custom development is quoted separately.

Get the app on the store page, or contact us to talk about your setup.

Share this article

  • User guide
  • Odoo 19
  • Odoo Community
  • Manufacturing
  • Gantt chart
  • Production planning
  • Work centers

The app in this guide

Manufacturing Gantt Chart app icon

Manufacturing Gantt Chart

MRP Gantt · Production Planning · Work Order Planning · Work Center Planning · Production Scheduling · Shop Floor Planni

View in store

Kalvyai Engineering · Engineering team

The engineers who build, connect and fix business systems at Kalvyai: Odoo, ERPNext, Shopify and AI agents that work inside them with approvals, budgets and an audit trail.

Comments

No comments yet. Questions and corrections are welcome.

Rate this post or leave a comment

Your rating (optional)
Not rated

Comments appear after an editor approves them. See our privacy notice.

Read next

WooCommerce Odoo Integration: Sync Rules, Stock, Orders, Taxes (cover)Technical
Kalvyai EngineeringOdoo

WooCommerce Odoo Integration: Sync Rules, Stock, Orders, Taxes

A practical guide to connecting WooCommerce and Odoo through the WooCommerce REST API: what to sync in which direction, how to push stock and prices, import orders safely, map taxes and avoid duplicate customers and orders.

8 min read

Tally to Odoo Migration: What to Move, Map and Check (cover)Technical
Kalvyai EngineeringOdoo

Tally to Odoo Migration: What to Move, Map and Check

A practical guide to moving from Tally to Odoo: which masters, balances, open invoices and stock to bring, what to leave in Tally, how to map ledgers and set up GST, and how to run a parallel month.

7 min read

Newsletter

Get new guides in your inbox.

Practical notes on Odoo, ERPNext, Shopify and AI agents, written by the engineers who build them. No spam, and you can ask to stop at any time.

Prefer a feed? Subscribe by RSS. We use your email only to send new articles. See our privacy policy.