User guide

Project Gantt Chart for Odoo 19: User Guide and Setup

How to install and use Project Gantt Chart (ki_gantt_project) on Odoo 19.0 Community. Covers task planning, dependencies with lag, auto-scheduling, critical path, baselines, milestones, workload and MS Project import.

Kalvyai Engineering · · 7 min read

Project Gantt Chart for Odoo 19: User Guide and Setup (cover)
On this page

Project Gantt Chart (technical name ki_gantt_project) adds a Gantt timeline to the Project app in Odoo 19.0 Community. You can plan tasks on the timeline, link them with dependencies and let the schedule move by itself when something slips. It also includes critical path, baselines, milestones, workload and resource planning, and import from MS Project, all inside your own Odoo database.

This guide covers who the app is for, how to install and set it up, and how to use each main feature step by step.

You can buy and download the module from the store page: Project Gantt Chart on the Kalvyai Store.

What the app is for

The standard Project app in Odoo Community is good for tracking tasks, but it gives you no Gantt view. That makes it hard to see the plan over time. Project Gantt Chart fills that gap. With it you can:

  • See every task of a project as a bar on a timeline.
  • Move, resize or drop tasks onto the timeline. Dates are saved at once.
  • Link tasks with Finish to Start (FS), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) dependencies, with lag.
  • Let auto-scheduling shift dependent tasks when an earlier task moves.
  • Highlight the critical path, the chain of tasks that sets the project end date.
  • Save baselines and compare the current plan against them.
  • Mark milestones.
  • Check workload and plan resources.
  • Import an existing plan from MS Project.

Who it helps

  • Project managers who want a real schedule in Odoo, not a separate planning file that drifts out of date.
  • Business owners who need a clear view of delivery dates and what is at risk.
  • ERP admins who run Odoo Community and want Gantt planning without changing edition.
  • Teams moving from MS Project who want to bring their existing plans into Odoo.

Requirements

  • Odoo 19.0. Other versions are not covered by this release.
  • Odoo Community edition.
  • The Project app installed.
  • A self-hosted Odoo server where you can add custom modules.

Installation

1. Get the module

  1. Go to the Project Gantt Chart store page.
  2. Buy the module and download the archive.

2. Add it to your addons path

  1. Extract the archive. You should get a folder named ki_gantt_project.
  2. Copy that folder into a directory listed in your Odoo addons_path.
Shell
# Example paths, adjust them to your server
cp -r ki_gantt_project /opt/odoo/custom-addons/
sudo systemctl restart odoo

If your custom addons directory is not yet in the config file, add it:

INI / config
[options]
addons_path = /opt/odoo/odoo/addons,/opt/odoo/custom-addons

Restart the Odoo service after any change to the config file.

3. Install the module in Odoo

  1. Log in as an administrator.
  2. Turn on developer mode.
  3. Open Apps and click Update Apps List.
  4. Remove the default "Apps" filter, then search for Project Gantt Chart or ki_gantt_project.
  5. Click Install.

You can also install it from the command line:

Shell
./odoo-bin -c /etc/odoo/odoo.conf -d your_database -i ki_gantt_project

Always test on a copy of your database first, especially if you plan to import existing projects.

Setup

After installation, check these points before your team starts planning:

  1. Access rights. Decide who can edit schedules and who can only view them.
  2. Working time. Check how the app handles working days and hours when it calculates dates.
  3. Resources. Make sure the people who do the work are set up so workload views show the right data.
  4. Where to find the view.

Using the Gantt chart

Open a project timeline

  1. Open the Project app.
  2. Open the project you want to plan.
  3. Switch to the Gantt view.

Each task with dates shows as a bar on the timeline. Tasks without dates appear in the To plan list.

Plan tasks from the To plan list

The To plan list holds tasks that do not have dates on the timeline yet.

  1. Find the task in the To plan list.
  2. Drag it onto the timeline at the date where it should start.
  3. Drop it. The dates are saved at once.

There is no separate save button for this. If you drop a task on the wrong date, just move it again.

Move and resize tasks

  • Move a task: drag the bar left or right. Start and end dates both shift, and the change is saved at once.
  • Change the duration: drag the start or end edge of the bar to make it shorter or longer.

If the task has dependencies and auto-scheduling is on, linked tasks may move too. See the auto-scheduling section below.

To create a dependency, drag from one bar to the next.

  1. Hover over the first task (the predecessor).
  2. Drag from that bar to the second task (the successor).
  3. Release. A link line appears between the two bars.

The app supports four dependency types:

Type

Meaning

Example

Finish to Start (FS)

B starts after A finishes

Pour foundation, then build walls

Start to Start (SS)

B starts when A starts

Start testing when development starts

Finish to Finish (FF)

B finishes when A finishes

Documentation finishes with development

Start to Finish (SF)

B finishes when A starts

Old system runs until new system starts

To change the type of an existing link:

Add lag to a dependency

Lag is a waiting time between two linked tasks. For example, with an FS link and 2 days of lag, the successor starts 2 days after the predecessor finishes. This is useful for drying time, supplier lead times or review periods.

  1. Open the dependency.
  2. Enter the lag value.
  3. Save.

Auto-scheduling

Auto-scheduling keeps the plan consistent when something slips. When you move or extend a task, tasks that depend on it move forward based on their link type and lag.

Example: Task A (Design) is linked FS to Task B (Build). If Design runs 3 days late and you extend its bar, Build moves 3 days later, and so does anything linked after Build.

Critical path

The critical path is the longest chain of linked tasks through the project. Any delay on a critical task delays the project end date. Tasks off the critical path have some slack.

  1. Open the project Gantt view.
  2. Turn on the critical path display.
  3. Critical tasks are highlighted.

Use this to decide where to put extra people or attention. Speeding up a non-critical task does not bring the end date forward.

Baselines

A baseline is a saved copy of the plan at a point in time, usually when the plan is approved. Later, you compare the live plan against it to see what has slipped.

  1. When the plan is agreed, save a baseline.
  2. As work goes on, show the baseline on the Gantt.
  3. Compare current bars against baseline bars to spot delays.

Milestones

Milestones mark key points such as a client sign-off, a go-live date or a delivery.

  1. Create or open the task that represents the milestone.
  2. Mark it as a milestone.
  3. Link it to the tasks that must be done before it, so it moves with the plan.

Workload and resource planning

The workload view shows how much work is assigned to each person over time, so you can spot overloads before they cause delays.

  1. Open the workload or resource view.
  2. Look for people with more work than their capacity in a given period.
  3. Fix overloads by reassigning tasks or moving them on the timeline.

Import from MS Project

If your plans live in MS Project, you can import them instead of retyping.

  1. Export the plan from MS Project in a supported format.
  2. In Odoo, open the import tool.
  3. Choose the target project and upload the file.
  4. Review the imported tasks, dates and dependencies on the Gantt chart.]

Test the import on a database copy first and check a few tasks against the original file.

Tips

  • Link tasks early. Auto-scheduling and critical path only work with the links you create. Unlinked tasks will not move when others slip.
  • Save a baseline at approval. Without one, you cannot show how far the plan has moved since it was agreed.
  • Keep the To plan list short. Undated tasks are invisible on the timeline and easy to forget.
  • Use lag instead of dummy tasks. For fixed waiting periods, lag keeps the plan cleaner.
  • Check workload after big moves. Shifting a block of tasks can overload someone in a different week.
  • Review the critical path weekly. It can change as tasks finish early or late.

Limitations

  • Built for Odoo 19.0. It is not listed for other versions.
  • Aimed at Odoo Community.
  • Requires a server where you can install custom modules.
  • Scheduling quality depends on your data. Wrong durations or missing links give a wrong plan.
  • MS Project import scope is limited to what the importer supports.

FAQ

Does it work on Odoo 17 or 18?

This release is for Odoo 19.0.

Are changes saved automatically?

Yes. When you move, resize or drop a task from the To plan list, the dates are saved at once.

Which dependency types are supported?

Finish to Start, Start to Start, Finish to Finish and Start to Finish, each with optional lag.

What happens to linked tasks when one task is late?

With auto-scheduling, dependent tasks move according to their link type and lag, so the plan stays consistent.

Can I bring in plans from MS Project?

Yes, the app includes MS Project import.

Do I need Odoo Enterprise?

No. The app is made for Odoo Community.

Where do I buy it?

On the Kalvyai Store.

How Kalvyai can help

We build and connect Odoo, ERPNext and Shopify systems, and our team has more than five years of experience with each. If you need help installing Project Gantt Chart, moving plans from MS Project, setting up resources and access rights, or adapting the module to your process, we can help. We can also add AI agents that work inside Odoo with human approvals, budgets and an audit trail, for example to flag slipping tasks or draft schedule updates for a manager to approve.

Contact us to talk about your project.

Share this article

  • User guide
  • Odoo
  • Odoo 19
  • Gantt chart
  • Project management
  • Odoo Community

The app in this guide

Project Gantt Chart app icon

Project Gantt Chart

Project Gantt Chart for Odoo Community: task planning, dependencies (FS, SS, FF, SF, lag), auto-scheduling, critical...

View in store

Kalvyai Engineering · Engineering team

The engineers who build, connect and fix business systems at Kalvyai: Odoo, ERPNext, Shopify and AI agents that work inside them with approvals, budgets and an audit trail.

Comments

No comments yet. Questions and corrections are welcome.

Rate this post or leave a comment

Your rating (optional)
Not rated

Comments appear after an editor approves them. See our privacy notice.

Read next

WooCommerce Odoo Integration: Sync Rules, Stock, Orders, Taxes (cover)Technical
Kalvyai EngineeringOdoo

WooCommerce Odoo Integration: Sync Rules, Stock, Orders, Taxes

A practical guide to connecting WooCommerce and Odoo through the WooCommerce REST API: what to sync in which direction, how to push stock and prices, import orders safely, map taxes and avoid duplicate customers and orders.

8 min read

Tally to Odoo Migration: What to Move, Map and Check (cover)Technical
Kalvyai EngineeringOdoo

Tally to Odoo Migration: What to Move, Map and Check

A practical guide to moving from Tally to Odoo: which masters, balances, open invoices and stock to bring, what to leave in Tally, how to map ledgers and set up GST, and how to run a parallel month.

7 min read

Newsletter

Get new guides in your inbox.

Practical notes on Odoo, ERPNext, Shopify and AI agents, written by the engineers who build them. No spam, and you can ask to stop at any time.

Prefer a feed? Subscribe by RSS. We use your email only to send new articles. See our privacy policy.